Boiler Room(5PZ990127)
Boiler Room(5PZ990127)
Quantity
-
+

Boiler Room(5PZ990127)

  • Installation Structure: The structure is installed with brackets secured to the building's exterior wall. Depending on strength requirements, additional support may include top tie rods or bottom columns (brackets use 100 mm C-channel steel). After the framework is completed, it is covered with painted iron plates.
  • Boiler Arrangement: Boilers are arranged according to the actual site dimensions, prioritizing safety and space efficiency in the planning.
  • Frame: Uses C-channel steel 150 type combined with 100 type.
  • Exterior Panel: Decorative board 350 type three-in-one panel (available in multiple colors for selection).
  • Aluminum Window: H80 x W110 cm, 1 unit.
  • Exhaust Fan: 16-inch, 1 unit.
  • Stainless Steel Drainage Channel: Length 570 cm, 1 unit, with a 2-1/2” drainage pipe configuration.
  • Front Door: Width 150 cm, height 230 cm, retractable steel roll-up door.
  • Rear Door: Width 150 cm, height 230 cm, retractable steel roll-up door.
  • Plumbing and Electrical Works:
    • a. Indoor lighting fixtures.
    • b. Boiler power supply box.
    • c. Maintenance power outlets.
    • d. Boiler water source setup.
  • Stairs: A stainless steel staircase must be installed next to the boiler room. Steps have a height of 18 cm and dimensions of 80 x 23 cm, leading from the first-floor plane to the roof of the 2nd floor, passing through the boiler room roof. Stainless steel handrails with a diameter of 1 inch are installed on both sides.